(1893)![]() This project involved an condition assessment of the masonry envelope. Our report indicated urgent repairs that were to be undertaken immediately. The project was split into two phases: Phase A encompassed the south and east elevations and was undertaken in 2008, while Phase B included the remaining north and west elevations and was completed in 2011. The completed project included: the removal and resetting of decorative brick veneer, with additional wall ties as was required; repointing wall joints and granite masonry; the restoration of the historic wood windows, doors and dormers wherever possible and replacement with new units were necessary. Project dates: 2008-11 |